Starts with a typical new US home: 2,150 sf over two floors with a two-car garage, a concrete driveway, gutters and basic landscaping. Change anything, add a deck, and the budget, savings, schedule and loan draws update instantly. No signup needed.
Planning-grade estimates based on national averages. Get real bids before you lock a loan amount.
Totals include site work, permits, well and septic, the driveway, gutters and yard you pick, and a 10% contingency, not just the house itself.
| Div | Item | Cost |
|---|---|---|
| Site & structure | ||
| 02 | Site prep & excavation | $22,937 |
| 03 | Foundation & flatwork | $50,461 |
| 06 | Framing materials & sheathing | $59,636 |
| 06 | Framing labor | $32,112 |
| Envelope | ||
| 07 | Roofing | $22,937 |
| 08 | Windows & exterior doors | $22,937 |
| 07 | Siding, stone & exterior trim | $27,524 |
| 07 | Gutters & downspoutsAluminum, about 184 ft · typical $1k–$3k | $2,024 |
| 07 | Insulation | $13,762 |
| Systems | ||
| 22 | Plumbing | $32,112 |
| 23 | HVAC | $27,524 |
| 26 | Electrical | $27,524 |
| Interior | ||
| 09 | Drywall | $22,937 |
| 12 | Cabinets & countertops | $27,524 |
| 09 | Flooring & tile | $22,937 |
| 06 | Interior doors & trim | $18,350 |
| 09 | Paint | $13,762 |
| 11 | Fixtures & appliances | $13,762 |
| Outdoor | ||
| 32 | DrivewayConcrete, 600 sf · typical $4k–$8k | $6,000 |
| 32 | LandscapingBasic: topsoil, seed and a few shrubs · typical $5k–$11k | $7,500 |
| Soft costs | ||
| 01 | Permits & impact fees | $13,587 |
| 01 | Engineering & plan changes | $4,500 |
| 01 | Builder's risk insurance | $2,294 |
| 33 | Well, septic & utility hookups | $25,000 |
| 01 | Contingency (10%) | $47,426 |
| Total build cost | $567,069 | |
Phases in order. DIY phases run longer because they happen on evenings and weekends.
Get at least three bids for each. Dashed trades are ones you're doing yourself.
A typical five-draw schedule. Your lender's may differ.
Foundation: Footings, walls and slab poured and inspected
Dry-in: Framed, roofed, windows in
Rough-ins: Rough-ins and insulation pass inspection
Drywall & trim: Walls finished, cabinets set
Final: Certificate of occupancy issued
Save this estimate.Create a free account to keep it as a project, then upgrade when you're ready to track spending, bids and draws against it.
Sign in to saveHow it works
The same kind of line-item breakdown a construction lender asks for, without the spreadsheet.
Square footage for each floor, garage and bonus space, your finish level and region, plus the driveway, gutters, deck and yard.
Self-supply materials or take on framing, wiring, drywall, paint, the deck or the landscaping and watch the savings add up.